Oregon Allows a Controversial Fracked Gas Power Plant to Begin Construction
View Date:2024-12-24 07:59:03
Columbia Riverkeeper and Friends of the Columbia Gorge asked a Multnomah County court on Monday to review a “grievously” unlawful decision by the Oregon Department of Energy to allow construction of the controversial Perennial Wind Chaser Station power plant. If built, the plant would be one of the state’s largest stationary sources of greenhouse gas emissions.
The nonprofit environmental groups alleged that the state allowed developers to avoid required stormwater and air pollution permits and meet a Sept. 23 construction deadline by breaking the construction into “phases.” They claimed that grading the site in preparation for an access road represented “phase 1” of the plant construction in a way that was never approved by a state siting panel.
If completed, the 415-megawatt, natural gas-fired power plant, near Hermiston in rural Umatilla County, 160 miles east of Portland, would provide additional power to the power grid to complement intermittent renewable sources, like wind and solar, at times of peak energy demand.
According to Columbia Riverkeeper, the plant would generate more than 1 million tons of carbon dioxide pollution annually, in addition to increased air pollution linked to cardiovascular and respiratory illness.
J.J. Jamieson, vice president of operations and development at Perennial Power Holdings Inc., said in an email that the company “is pleased to move forward in the next steps of the Wind Chaser Station project, on our way to providing the Northwest with reliable energy that will set the stage for sustainable energy technologies in the future.”
He called the project “an ideal energy solution for the state of Oregon and greater Northwest region.”
After years of opposing the project, environmental groups now hope a combination of legal action and grassroots organizing can help them shut down Perennial’s construction.
A Power Plant With No Customers
The plant was first proposed six years ago by a subsidiary of one of Japan’s major industrial conglomerates, Sumitomo Corporation. That was well before Oregon adopted ambitious statewide goals for carbon emissions and greater offset payments for mitigating greenhouse gas pollution that would make the natural gas-burning electric utility considerably more expensive to operate.
But since the adoption of such goals, environmentalists have only found it harder to stop the proposed plant as it moved through the state regulatory process.
The plant’s developers envision operating it no more than 4,400 hours per year at full load by burning natural gas delivered via the nearly 1,380-mile-long Gas Transmission Northwest pipeline. The existing pipeline, owned by TC Energy, transports Canadian natural gas to communities in Washington, Oregon and California.
Five years out from the plant’s initial approval in 2015, developers have yet to secure a buyer for the electricity the plant would produce, though they remain in dogged pursuit.
Finding a market for the plant’s output in Oregon, where hydropower and other renewable energy sources account for a majority of the state’s utility-scale net electricity generation, has probably become more difficult amidst stricter statewide energy standards and a pandemic that has depressed overall natural gas demand.
Environmentalists contend this lack of a market should be proof enough that the plant need not go forward. Still, they say, they find themselves having to use every legal device at their disposal to keep it from proceeding.
‘Baffling’ Decision by State Called Into Question
The latest court action on Monday came days after activists sent a letter to Gov. Kate Brown and Janine Benner, head of the Energy Department, asking them to terminate the plant’s permit and investigate the department’s approval process.
Nathan Baker, a senior staff attorney for Friends of the Columbia Gorge, said that the petition filed Monday seeks “a judicial determination that the Perennial site certificate is expired and must be terminated” and that prohibits “any further site work on this project unless and until a new site certificate is issued.”
Dan Serres, Columbia Riverkeeper’s conservation director, said he found it baffling that Oregon has allowed Perennial to move forward with the plant despite its apparent violations of state law and amidst concerns over its impacts on the global climate, local environment, and nearby communities.
It is astonishing, he said, “for Oregon, which prides itself on trying to address climate change, to be holding the door open for this very large polluter.”
If the state had found that developers missed their Sept. 23 construction deadline and required them to apply for another site certificate extension, Perennial would have been subject to an updated offset rate of $2.85 per ton of carbon emitted by the plant, rather than the $1.90 per ton rate in effect when it received its amended site certificate in November 2019.
Allowing the plant to proceed under its current certificate saved developers as much as $11 million a year “at much greater harm to the environment,” Columbia Riverkeeper said in a statement.
How Green is Oregon?
Oregon has sought to brand itself a climate leader under Gov. Brown’s administration.
Earlier this year, Brown signed an executive order directing state agencies to take action to help meet greenhouse gas reduction goals of at least 45 percent below 1990 emissions levels by 2035 and at least 80 percent below 1990 levels by 2050.
The state’s Renewable Portfolio Standard also commits Oregon to sourcing 50 percent of its electricity from renewables by 2040, while legislation has also committed the state to phasing out electricity generated from coal by 2030.
But constructing a new gas power plant, one that would join the state’s top greenhouse gas polluters, seems to directly contradict those goals.
Despite the state’s progressive reputation on climate, some environmentalists suspect the state’s relationship with developers may help explain Perennial’s progress.
Dineen O’Rourke, campaign manager of 350 PDX, which is part of the Pacific Northwest-based Power Past Fracked Gas coalition, said the group was concerned that staff from the Oregon Energy Facility Siting Council were “a little too cozy with the developers of the project,” adding, “We see that as a possibility for why this is moving forward so quickly.”
Jennifer Kalez, a spokesperson for the Department of Energy, sharply disputed the contention that state officials had been in any way co-opted.
“Oregon Department of Energy staff are dedicated public servants, who work hard to ensure the laws and rules for siting large energy facility projects in our state are followed, regardless of the type of facility being built,” she said in an emailed statement, adding that the efforts of siting council members “are also focused on making sure proposed, approved, and operating facilities follow their standards.”
“Any suggestion otherwise is categorically false,” said Kalez.
‘A Disaster for Oregon’s Climate Goals’
While natural gas offers a cheaper and cleaner alternative to other fossil fuels like oil, it’s far from climate-friendly.
Serres of Columbia Riverkeeper said Perennial’s projected carbon emissions represent only “a slice of the pollution” it entails.
He said there could be additional climate impacts from methane leaking along the supply chain for the Perennial station. A study published in 2018 found that emissions from the U.S. oil and natural gas supply chain from methane leakage were 60 percent greater than the U.S. Environmental Protection Agency inventory estimated.
Methane, a primary component of natural gas, is a greenhouse gas 84 times more potent over a 20-year period than carbon dioxide. On top of emissions, the process of hydraulic fracturing, or “fracking,” to extract natural gas raises numerous environmental concerns, including contamination of local water supplies.
Serres also said the Perennial plant could also produce volatile organic compounds, which contribute to low-level ozone or smog formation—already an issue in the Columbia River Gorge.
“This entire project is a disaster for Oregon’s climate goals,” said O’Rourke, of 350 PDX.
Lisa Arkin, executive director of the nonprofit, statewide environmental justice organization Beyond Toxics, also raised concerns about the potential health harm to communities where the fracked gas fueling Perennial, which would be delivered via a natural gas pipeline lateral tapping into the existing Gas Transmission Northwest pipeline, is being mined.
“The potential for pipes leaking, breaking, polluting water is just an unacceptable environmental and human health risk,” said Arkin, noting the project’s proximity to the Columbia River.
Climate Activists Forge Ahead
Though developers and state officials have effectively dismissed claims that Perennial violated state law, environmentalists believe they can make a strong case showing otherwise.
Baker, Friends of the Columbia Gorge’s senior staff attorney, said Perennial failed to comply with numerous preconstruction conditions of its site certificate and state regulation necessary to lawfully start construction on any part of the project.
“What they’ve done by conjuring up this legal fiction of starting construction by only building a road is to extend their time by which they can build the project,” said Baker.
Such action, he said directly contradicts the Oregon’s Legislature’s intent to prevent developers from “site banking,” or locking up sites for state-approved energy facilities they may never complete.
Jamieson said Perennial was “working within all legal requirements and state regulations laid out by the Oregon Department of Energy, Oregon Department of Fish and Wildlife, and other organizations to meet the conditions of our certificate.”
Kalez, the Energy Department spokesperson, said Perennial satisfied its phase 1 pre-construction conditions with the siting council on Sept. 18 and that those conditions did not include the stormwater permit referenced by environmental groups.
She also said the DOE had inquired with Oregon’s Department of Environmental Quality about Perennial’s stormwater permit requirements and could initiate enforcement action if there was evidence that the developers “failed to obtain a necessary permit or to comply with an applicable site certificate condition at any time during the construction or operation of a facility.”
But environmental advocates, in their Oct. 30 letter to Gov. Brown and Energy Director Benner, called the Energy Department’s position “erroneous” and maintained that the DOE staff “not only failed to ensure that the site certificate conditions were being followed, but in fact facilitated Perennial’s law-breaking actions.”
Serres called on Gov. Brown to hold DOE and Perennial accountable for actions that he said violate the Clean Water Act, jeopardize state climate goals, and “fundamentally undermine the public’s trust in our agencies’ and leaders’ commitment to protecting Oregon’s climate and upholding the law.”
If the legal case against Perennial fails, pure economics may yet succeed in shutting the plant’s construction down and delivering opponents an environmental victory.
Baker said “it’s at best unclear whether the Perennial developers actually intend to build this project,” given that they still lack a power purchaser.
“I don’t anticipate that demand for new power projects will go up in the near future,” he said, “and it seems as if Perennial doesn’t anticipate that either or else they would have lawfully started construction or applied for another extension of the construction deadline.”
veryGood! (564)
Related
- Jessica Simpson's Husband Eric Johnson Steps Out Ringless Amid Split Speculation
- Gloria Allred representing family involved with Josh Giddey case
- Older Voters Are Second Only to Young People in Share of ’Climate Voters,’ New Study Shows
- U.S. imposes sanctions on three Sudanese figures with ties to former leader Omar al-Bashir
- Beyoncé nominated for album of the year at Grammys — again. Will she finally win?
- North Carolina candidate filing begins for 2024 election marked by office vacancies and remapping
- U.S. imposes sanctions on three Sudanese figures with ties to former leader Omar al-Bashir
- 12 books that NPR critics and staff were excited to share with you in 2023
- Michelle Obama Is Diving Back into the Dating World—But It’s Not What You Think
- Jaguars QB Trevor Lawrence sprains right ankle in 34-31 overtime loss to Bengals on MNF
Ranking
- Rafael dissolves into a low pressure system in the Gulf of Mexico after hitting Cuba as a hurricane
- Prince Harry challenges UK government’s decision to strip him of security detail when he moved to US
- Grand Theft Auto VI leak followed by an official trailer with a twist: A release date of 2025
- Wikipedia, wrapped. Here are 2023’s most-viewed articles on the internet’s encyclopedia
- Francesca Farago Details Health Complications That Led to Emergency C-Section of Twins
- Christmas shopping hangover no more: Build a holiday budget to avoid credit card debt
- Remains found in Indiana in 1982 identified as those of Wisconsin woman who vanished at age 20
- Detroit-area performing arts center reopens after body is removed from vent system
Recommendation
-
Megan Fox and Machine Gun Kelly are expecting their first child together
-
NHL Stanley Cup playoff bracket: League standings, potential first-round matchups
-
Ukrainian officials say Russian shelling has hit a southern city, killing 2 people in the street
-
76ers’ Kelly Oubre Jr. scoffs at questions about legitimacy of his injury, calls hit-and-run serious
-
FC Cincinnati player Marco Angulo dies at 22 after injuries from October crash
-
Government, Corporate and Philanthropic Interests Coalesce On Curbing Methane Emissions as Calls at COP28 for Binding Global Methane Agreement Intensify
-
Virginia officials certify 2023 legislative election results, other electoral contests
-
Heisman finalists: LSU QB Daniels, Oregon QB Nix, Washington QB Penix Jr., Ohio St WR Harrison Jr.